The Premier Inn at the Three Bells, Hordle, can grow from 20 to 57 bedrooms. Permission was issued on 24 November, with 27 rooms in a new two-storey building.

The Premier Inn at the Three Bells on Silver Street, Hordle, has permission to grow from 20 bedrooms to 57. New Forest District Council issued the decision on Tuesday 24 November.

The extra 37 rooms come in two parts:

  • 10 bedrooms on the first floor, made by converting part of the existing pub and restaurant
  • 27 bedrooms in a new two-storey building at the back of the site

The bar and restaurant on the ground floor will be reconfigured, with new plant and linen storage. The details are in the officer report to the August planning committee.

The decision is on the council’s planning register under 26/10136.

How it was decided

The planning committee backed the scheme on 12 August, subject to a legal agreement, the minutes show. The agreement secures contributions to habitat mitigation and Bird Aware Solent, which protect the coast and the forest from extra visitors. It is dated 23 November, the day before the permission was issued.

Hordle Parish Council recommended permission. Its councillors noted that the hotel employs local people and that guests support the area’s tourist economy. They also said the scheme would renovate the old frontage and improve the street scene, the report says.

The parish council did flag the site exit. It is close to the Pennys Corner roundabout, where the road splits into two lanes.

The report records objections from five households. Their concerns included noise from air conditioning and other plant, traffic, light and loss of privacy.

What changes for parking

The car park will shrink from 78 spaces to 57, one for each bedroom. Officers said that meets the council’s parking standards. Hampshire County Council’s highways team did not object.

The applicant’s transport statement said the bigger hotel would not need any extra staff, according to the report. Officers said the work would create construction jobs and secure the jobs of existing staff.

Why a 2014 plan was refused

An earlier plan to enlarge the hotel was refused in 2014. That scheme extended the main building and would have meant the loss of the house next door. Much of the site was also in the Green Belt then, which no longer covers it.

The report says the new scheme is different: the extra rooms go in a separate building set back into the site, and the house next door is kept.

What it means for you

  • The Three Bells keeps a bar and restaurant, reconfigured on the ground floor, according to the plans.
  • No start date has been published. The permission sets conditions on construction, including a construction management plan.

The papers