New tidal flaps are in at Lymington's Toll Road flood defences, which protect 140+ properties. One valve stays shut until new floats arrive, so marshes sit lower.
The Environment Agency has finished replacing the tidal flaps at Lymington’s flood defences, in time for the winter flood season. The two-year project at Toll Road also refurbished the flood gate that can be shut to keep flood water out of the town.
More than 140 properties are protected by the Lymington Flood Alleviation Scheme. The agency announced the work was complete on Wednesday 7 October.
One part is not finished. A valve that manages water levels in the marshes has been shut as a precaution until replacement parts arrive. Residents may notice lower water in the marshes until then.
What has been done
The original steel flaps went in about 18 years ago, when the flood scheme was built. They had reached the end of their design life and were heavily corroded in places, the agency said.
Specialist divers inspected them underwater before new ones were designed. The new flaps are made of high-density polyethylene and marine-grade stainless steel. They were fitted in September 2026 at low tide, using divers and a crane.
At the same time the agency:
- repainted the Toll Road flood gate
- replaced its worn seals
- improved access for people on foot when the gate is closed
- laid a new, quieter road surface
The work was planned outside school holidays to keep disruption down.
The valve that is still to be fixed
During the project the team found leaking floats in the regulating valve. That valve controls water levels in the marshes. The agency says it is particularly important for flood risk in winter.
Replacement floats have been ordered. Until they are fitted, the valve stays closed and the marshes will sit lower than usual. The agency says the valve will be repaired by the end of the year, and normal operation will then resume.
Artur Podsiadly, the agency’s project manager, said: “We recognise that residents may notice lower water levels in the marshes while the regulating valve is temporarily closed. We have ordered replacement floats and will complete this work when conditions allow.”
How this fits with last year’s work
This is the second phase of work on the scheme. The first was in November 2025, when the agency replaced the flood gate’s loose sill plate on Toll Bridge Road. That job closed the road overnight for six days. At the time it said a second phase replacing the tidal gate mechanisms would follow in 2026.
The agency’s 2025 notice gives the background:
- Lymington floods when high river levels coincide with high tides and the river overtops its banks.
- The flood gate was installed in 2008 as part of the flood scheme.
- It has been closed several times as a precaution since then.
- It was last needed for real during the winter floods of 2013/14.
The scheme also includes piling along the edge of the marshes to protect nearby homes.
What it means for you
- If you live near the marshes, the low water you may see over the coming weeks is deliberate. It is not a fault or a leak. The agency expects to reopen the valve by the end of the year.
- If you use Toll Road, the gate works are done. The road has a new surface, and there is better access on foot for the times the gate is shut.
- Before the winter, it is worth signing up for free flood warnings by phone, text or email. You can check the current flood risk for Lymington at any time.
- Questions about the works went to the agency’s Hampshire team at SLTSDN.AP.West.Hants@environment-agency.gov.uk during last year’s phase.
For road closures across the district this week, see our New Forest roadworks and travel page.
Sources
- Environment Agency: Major improvements to Lymington flood defences completed, 7 October 2026, for the flaps, the gate works, the valve and the 140 properties.
- Environment Agency: Lymington flood defences to be strengthened with repairs, 3 November 2025, for the first phase and the scheme’s history.