New Forest District Council's cabinet has approved £7.755m for Ringwood Market Place and Market Square. Work is expected to start in winter 2028/29.
New Forest District Council’s cabinet has approved £7.755 million for Ringwood Market Place and Market Square, the council said on Wednesday. Building work is expected to start in winter 2028/29, once design, approvals and public engagement are complete.
The money comes from the Community Infrastructure Levy (CIL), which developers pay towards the infrastructure that growth needs. It is the decision we previewed on Monday.
Ringwood Town Council called the scheme, known as Thriving Market Place, “a once-in-a-generation opportunity to revitalise the historic heart of Ringwood”. It says the idea grew out of the town’s Neighbourhood Plan.
“A major milestone”
The Town Mayor, Councillor Mary DeBoos, said in the town council’s statement:
“We are delighted that New Forest District Council has approved this significant investment in Ringwood’s future. Securing this level of funding is a major milestone and demonstrates confidence in the long-term future of our town centre. It provides the opportunity to deliver an ambitious project that will enhance one of Ringwood’s most important public spaces and help ensure it continues to serve residents, businesses and visitors for many years to come. Thanks are owed to all those who worked on the Ringwood Neighbourhood Plan and in particular Cllr Janet Georgiou who led the Town Centre elements of the plan.”
The decision falls in the market’s anniversary year. The town council’s history of the market says the right to hold a market on Wednesdays was granted in March 1226, and that the weekly market has run continuously since. Cllr DeBoos said:
“It is particularly fitting that this announcement comes in the year that Ringwood is celebrating the 800th anniversary of its Charter Market, recognising the central role the market has played in the life and prosperity of the town for eight centuries. We look forward to continuing to work closely with New Forest District Council, Hampshire County Council and our community as the project moves forward.”
Cllr Derek Tipp, the district council’s portfolio holder for planning and economy, said:
“Ringwood’s Market Place sits at the heart of the town and plays an important role in its identity and economy. This funding allocation is an important milestone that allows us to continue developing the project and move towards delivery. The ambition is to create a high-quality public space that supports local businesses, strengthens the town centre and provides lasting benefits for residents and visitors. We know there is strong interest in the future of the marketplace and we are committed to making sure the project is progressed in a way that delivers the best possible outcome for Ringwood.”
What the money pays for
The cabinet report splits the £7.755 million in two:
- £6.325 million for construction and delivery
- £1.430 million for design, project management and professional fees
Both sums include a 10% contingency. The report warns that the estimates are at an “early stage” and could change with utility diversions and site surveys.
The money covers the Market Place and Market Square phases only. An August report put the whole project at £11 million to £12 million.
The district council says the plans include:
- a more pedestrian-friendly environment
- better access between the Market Place, the High Street, The Furlong and surrounding areas
- space for markets, outdoor dining, festivals and events
What happens next
The scheme now moves to design, consultation and delivery planning. The report’s draft programme, dated October 2026, starts with site investigations and consultation in December 2026. Preliminary design follows in February 2027 and detailed design in October 2027.
Approvals from asset owners are pencilled in for May 2028 and procurement for June 2028. Public engagement and construction are timed from January 2029 and last 13 months, with handover from March 2030. The programme ends in March 2031.
The report calls the winter 2028/29 start a “working assumption”. It depends on funding, approvals and the results of consultation.
Neither council’s statement says how many parking spaces would go, how traffic would be routed, or where the market would trade during the works.
The other schemes
The same report put eight other projects forward for further work, including schemes in New Milton, Lymington, Fordingbridge and Netley Marsh. We listed all eight on Monday. Today’s statements do not say what cabinet decided on them, and the formal decision record was not on the council’s site when we checked on Wednesday night. Under the report’s recommendations, none would get money until a full business case came back to cabinet.
What it means for you
- If you shop, trade or park in Ringwood, nothing changes yet. Work is not expected on site for at least two years.
- If you have a view on the design, the draft programme puts the first consultation in December 2026. Neither council has published dates so far.
- If you trade at the market, ask how the works will be phased when the consultation opens. The town council’s contact details are on its website.
We will report the consultation dates when they are published.
Sources
- New Forest District Council, Major investment approved for Ringwood Market Place regeneration, 4 November 2026.
- Ringwood Town Council, press release, 4 November 2026.
- New Forest District Council, Cabinet 4 November 2026, Strategic CIL: allocation of funds to projects, including Appendix 4 (draft programme).